Header Ads

PNG LNG OFFSHORE PIPELINE COMPLETE

Image Credit: Esso Highlands Media and Communication Unit
The PNG LNG Project’s offshore pipeline is now complete following the final tie-in to the onshore pipeline in December 2012.

The final tie-in – or connection – took place at the Omati landfall in the Omati River where the pipeline from the land (onshore) meets with the offshore (undersea) pipeline.

The offshore pipeline is approximately 407 kilometres long and connects to the 292-kilometre-long onshore pipeline, which begins at Hides.

Welding of the offshore pipeline began in October 2011; since then the progress has been rapid.

“This is another example of the progress being made across the PNG LNG Project, despite difficult conditions,” said PNG LNG Project Executive Decie Autin. “We are just over 75 percent complete across the entire Project and on target for first gas deliveries in 2014.”

Ms Autin attributes the progress to the company’s most important resource: people. 

”Our accomplishments have only been possible because of the extensive efforts of a strong team who have pulled together to make this Project possible,” she said.


Elsewhere in the Project, the 2.4km jetty at the LNG Plant Site is almost complete, and hydrotesting of the two LNG tanks is underway.

The major activities coming up for 2013 include the completion of the Komo Airfield and onshore pipeline, continuing construction of the Hides Gas Conditioning Plant, and ongoing drilling activities... 

Esso Highlands Media and Communications Unit

Powered by Blogger.